Ex-kitchen, bathrooms, flooring and doors were removed and disposed.
First fix plumbing works in the bathrooms and kitchen
New kitchen cupboards & appliances supplied and installed
All switches & sockets replaced with the new ones.
All downlights were replaced with the new ones.
Wall & floor tiling of bathrooms were completed
Natural stone worktop & splashback supplied and installed to the kitchen.
Painting walls and ceilings completed
All electrical works certified.
Second fix plumbing works completed
New timber flooring installed.
Ex skirtings were reinstalled and painted.
New doors and door accessories were installed.