Preparation works (Walls & floors) of x6 Bathrooms and x1 WC
Supply materials and create niches in the shower areas
Supply and do the waterproofing works of x6 Bathrooms and x1 WC
Supply auxiliary materials and do the floor tiling works of x6 Bathrooms (Walk-in showers) and x1 WC
Supply auxiliary materials and do the wall tiling works of x6 Bathrooms (Walk-in showers) and x1 WC
Supply materials and sand & varnish the wooden ornaments around x4 fireplaces
Supply and install new MDF skirtings
Supply and install a new drywall to the bedroom at 2nd floor
Supply and install new ceiling in dressing room at 2nd floor
Supply and install suspended ceiling band for led lights in master bedroom
Supply and plaster the new wall & ceilings in the master bedroom at 2nd floor
First fix electrical works at 2nd & 3rd & 4th floors
First fix electrical Works at basement floor.
Supply and plaster the walls & ceiling (Except elevator located stairways & stair halls)
Supply and paint the walls & ceiling & woodworks (Except elevator located stairways & stair halls)
Repairing the non-working sash windows (upper + lower parts) at all floors