Skip to main content

Full refurbishment works of high-end flat (x5 Bedrooms)at high street kensignton

Demolition Works (Material + Labour)

Supply and install stud walls in WC/shower room & hall

Supply and install suspended ceiling (Living room)

Supply and install suspended ceiling (Kitchen & WC/Shower)

Supply and install suspended ceiling (entrance hall)

Supply and plaster new ceilings & new walls

Preparation works of bathroom walls & floors (for walk-in showers)

Supply and do the waterproofing works in bathrooms & WC (x5 Bathrooms & x1 Toilet)

Supply and install ditra mat to the bathroom floors (x5 Bathrooms & x1 Toilet)

Supply auxiliary materials and install floor tiles in wet areas (x5 bathrooms & x1 WC & x1 Kitchen)

Supply auxiliary materials and install wall tiles (x5 Bathrooms & x1 WC & x1 Kitchen)

Removal and disposal of floorboards (90m2) and supply & install 100 mm Rockwool between joists

Supply and install 12mm new plywood and level the floors (90m2)

Supply and install 17mm sound barrier (90 m2)

Install new timber flooring (90 m2) (Plank) (Labour Only)

Install new internal doors (Labour Only)

Supply auxiliary materials and install new timber skirtings

Supply and paint the walls & ceilings

First and second fix electrical works

Install the vanity units in the bathrooms & toilet

Install the carpets (Labour Only)

Supply & Repair & paint the walls & ceilings of the fire escape stairs (from the building entrance up to the 3rd floor) at the end of works

Install data cables under floor (Labour only)

Supply and install timber framed raised floor for bathrooms & technical room.

Supply and plaster the walls at skirting height of all rooms

Adjustment of door openings (x18 doors) according to the new door sizes

Supply and install new acoustic raised floor, install new acoustic suspended ceiling and install acoustic wall foams (Technical room)

Install Schluter KERDI boards to all bathroom & WC walls (Labour Only)

Supply and install 75mm Rockwool sound bloc under the existing plywood in the kitchen

Install x6 Access panels to the walls (In bathrooms and corridor) (Labour Only)

Supply and replace plasterboards in x2 Bathrooms with 5.5mm Plywood (for hand douches)

Supply and install additional timber frame & plywood for the bathtub in bathroom-5

Supply and repair all radiator boxes